Reduction of project deadlines
A challenge from ISA REP
Deadline to apply:
Fecha abierta
How could we create new ways to reduce the social impact during the construction of projects? How could we improve the construction methods of the assembly process of power lines and pylons? How can we reduce the effective construction time and deliver our projects on time or even ahead of schedule?
CONTEXT OF THE PROBLEM
Due to the rapid growth of the country and the migration of the Peruvian population to new areas, the growth of electricity demand was a forced reality. For this reason, the construction projects of new power lines and substations must connect generators, distributors and customers in the shortest possible time, complying with the expected deadlines. However, currently our construction deadlines for high-voltage power line and substation projects have a compliance rate of 97%, with a CAPEX compliance overcost of 3.5% in regard to the established amounts. This situation has represented additional costs in the last years of 10 MM USD. The problem of small delays is due to two important factors. The first factor is related to the social impact on construction projects, since we do not have an optimal way to bond with all the communities around our project area and make them our allies. This has meant delays of more than 06 months in our most representative projects. The second factor is the construction methods used by us. Fro this reason, we seek to break the traditional way of building projects and thus reduce the critical route times, especially in rugged and remote areas.
DESCRIPTION OF THE PROBLEM
The breach of project deadlines and cost overruns results in delays in the formation of new lines and causes economic impacts for ISA REP.
FREQUENCY OF THE PROBLEM
Construction deadlines for high-voltage power line and substation projects are met at 97%, with a cost overrun CAPEX of 3.5% in relation to the established amounts.
PARTIAL SOLUTIONS
IMPACT OF THE PROBLEM
This has represented additional costs in the last year of 10 MM USD.
QUANTIFICATION OF THE PROBLEM
–